Massachusetts ties data center permits to clean power and local approval

Massachusetts ties state permits for data centers over 25 MW to clean power supply and community approvals. EO 658 guides.
Massachusetts ties data center permits to clean energy, grid costs

Massachusetts has introduced new regulations tying state permits for substantial data centers to their power sources and community agreements. These rules apply to projects exceeding 25 megawatts (MW) of power usage.

This week, Governor Maura Healey enacted Executive Order 658, which mandates the state’s environmental protection agency to create protocols for data centers to secure enough new clean electricity to cover their annual energy consumption.

For data center operators and IT organizations planning large AI and cloud deployments, this order adds a new layer of complexity. In addition to land, fiber, water, interconnection, and construction plans, they must now consider power procurement, grid costs, and community approval.

“Massachusetts is moving beyond asking who pays for a large load and toward asking what a project must prove before the system relies on it,” said Neil Osnato, founder of Persistence Analytics Group, an infrastructure analytics and advisory firm.

The order applies to data centers built or expanded after September 8 that exceed 25 MW of peak electric demand, including expansions reaching this threshold.

Understanding the Mechanisms of EO 658

Data centers must source electricity that meets the state’s Clean Energy Standard. By December 31, the Massachusetts Department of Environmental Protection (MassDEP) will also set an alternative payment fee for projects not generating incremental clean electricity. This fee will contribute to a Ratepayer Protection Fund to offset electricity supply costs.

For data center operators, securing power becomes a critical part of project development. Osnato highlighted the importance of verifying the source, novelty, and deliverability of energy resources for large campuses.

Requiring Developers to Verify Power Sources

The order builds on a June framework encouraging data centers to provide or procure clean energy to meet their full demand.

Developers can meet the EO 658 requirements by procuring incremental new clean electricity generation. The generation does not need to come from a dedicated plant on-site.

Massachusetts aims to measure requirements against annual electricity consumption rather than hourly matching of generation and load, allowing reliance on the grid for capacity and reliability.

Several aspects remain undecided, such as what qualifies as new generation, the consequences of project delays, and how to prevent double-counting clean-energy attributes.

Balancing Grid Costs and Project Viability

The clean-power mandate seeks to prevent data center projects from inflating power costs for other customers. EO 658 instructs the Massachusetts Department of Public Utilities (DPU) to devise large-load rate schedules to avoid passing distribution-grid upgrade costs onto other ratepayers.

The DPU is also tasked with creating measures to eliminate speculative projects from utility interconnection queues, ensuring only viable projects consume resources.

“If a 25+ MW project must put up fees, deposits or other evidence demonstrating that it’s legitimate before consuming utility study and interconnection resources, Massachusetts is implicitly recognizing something the industry is dealing with nationally,” Osnato said.

The Prerequisite of Local Approval

EO 658 requires projects to align with the state’s data center framework and submit a community benefits agreement before acquiring state permits.

Healey’s administration emphasized that local approval is essential before seeking state permits. The order also restricts nondisclosure agreements with data center projects, except where law permits.

The order permits certain exemptions, including those linked to accredited institutions or state-sponsored programs. Additionally, environmental protocols will address water quality and quantity, and greenhouse gas emissions will be evaluated against the state’s Clean Energy and Climate Plan.

Markley Group, a long-standing data center operator in Massachusetts, expressed support for the uniform development standards. “We support policies that bring clarity and consistency to how data centers are permitted and developed in the Commonwealth,” said Jeff Markley, CEO.

Former U.S. Energy Secretary Jennifer Granholm praised the framework on LinkedIn, highlighting its strength in balancing AI’s economic potential with community and ratepayer protection.

Granholm commended Massachusetts’ clean-energy requirements and developer responsibilities, noting Gov. Healey’s balanced approach. “She isn’t reflexively saying ‘no’ to data centers, and she isn’t writing them a blank check either,” Granholm remarked.