US Offshore Wind Projects Overcome Legal Hurdles to Resume Construction

The US offshore wind industry wins court battles, allowing five major projects, including Sunrise Wind, to proceed.
5 offshore wind farms move ahead after Trump admin misses appeal deadline [update]

The future of offshore wind projects along the US East Coast has taken a decisive turn. The US Department of the Interior has chosen not to appeal court rulings that greenlit the continuation of five major wind farm projects initially halted by the Trump administration over national security concerns.

Offshore Wind Projects Resume

April 10, 2026: The Trump administration’s December 2025 directive to halt five significant offshore wind projects faced immediate legal challenges. Among the affected were Sunrise Wind, Vineyard Wind, Coastal Virginia Offshore Wind, South Fork Wind, and Revolution Wind. All projects received court injunctions to continue construction despite the federal halt order.

Interior Secretary Doug Burgum contemplated appealing these judicial decisions. However, political negotiations over a crucial energy permitting reform bill led him to let the appeal deadline pass. This decision allows the projects, with a combined capacity to power over 2 million homes, to proceed, marking a significant win for the US offshore wind sector.

Legal Battles and Court Rulings

February 2, 2026: The Sunrise Wind project, a 924-megawatt endeavor by Ørsted and Eversource, was cleared to resume by US District Judge Royce Lamberth. The judge’s injunction permits ongoing construction while the project remains embroiled in legal proceedings. Sunrise Wind, along with the other four projects, has effectively countered the federal order, which developers criticized for lacking proper procedural backing.

Ted Kelly from the Environmental Defense Fund highlighted the financial benefits of such projects, noting that the existing portion of Vineyard Wind saved New Englanders $2 million daily during harsh winter conditions. He questioned the rationale behind administrative actions that hinder renewable power advancements.

Progress and Impact

January 27, 2026: The Vineyard Wind project, already 95% complete, received clearance from US District Judge Brian Murphy to resume operations. This decision marks another defeat for the administration’s attempt to stall offshore wind developments. The rulings against the federal halt order underscore the courts’ stance that the Interior Department inadequately justified its national security concerns.

Individual Project Details

Revolution Wind

Owned by Ørsted and Global Infrastructure Partners’ Skyborn Renewables, Revolution Wind is nearly finished, with 87% of construction complete. The project aims to deliver power to over 350,000 homes and is backed by agreements with the Department of Defense and Air Force after comprehensive permit reviews. Any delay could impact power pricing and grid reliability in the Northeast.

Empire Wind

Empire Wind, developed by Equinor, has also contested the suspension order, emphasizing the potential for significant commercial impacts. The project is over 60% complete and poised to provide electricity for approximately 500,000 homes. Its development is closely tied to New York’s energy strategy, and Equinor has invested heavily in its completion.

Read more: Trump admin sued for halting work on the US’s largest offshore wind farm

Original Story at electrek.co