The 12 largest planned gas power projects in Texas are designated for data center operations, as reported by Global Energy Monitor (GEM), a nonprofit that tracks energy infrastructure.
The GEM report highlights a 50% increase in gas power generation projects in Texas over the past six months, exceeding growth in most countries except the United States.
Permitting documents indicate that several large-scale projects could emit over 100 million tons of greenhouse gases annually, equivalent to the emissions of a mid-sized industrialized nation. These projects may also release tens of thousands of tons of other pollutants.
GEM’s Global Oil and Gas Plant Tracker reveals 81.7 gigawatts (GW) of operational gas power in Texas, with 99.4 GW in development and an additional 22.4 GW recently announced.
“This surge in gas proposals faces challenges from a constrained gas market,” stated Jenny Martos, project manager for the tracker. “It is increasingly difficult to determine which proposals will be realized.”
The GW Ranch Energy Center near Fort Stockton received the largest air pollution permit in the U.S. this year, projecting emissions of 33 million tons annually. Amazon recently acquired the project.
In the Texas Panhandle, Fermi America’s Project Matador, backed by former Texas Gov. Rick Perry, plans to construct 90 combined-cycle gas turbines and associated infrastructure, with projected emissions of 24 million tons annually. Southeast Texas’s Nexus Data Center Hubbard is expected to emit 22 million tons annually.
Due to a global supply backlog for combined-cycle turbines, developers are using smaller, less efficient simple-cycle turbines. GEM notes these options have higher emissions per unit of electricity generated.
In West Texas, the Kilby Power Plant plans to release 12 million tons annually using two combined-cycle and 15 simple-cycle turbines.
In the Panhandle, Westline 2335 proposes emissions of 10 million tons annually from 240 generators, while Roman Energy Center projects 8 million tons annually using 640 generators and 25 diesel engines.
The Longhorn Power Plant in Abilene plans emissions of 8 million tons annually to power data center buildings. Other projects, like Schlachter Realty, are not disclosing expected emissions.
Texas Gov. Greg Abbott has urged data center developers to build independent power plants to prevent strain on the state’s electrical grid. He recently announced a pause on new proposals, warning against disrupting local communities.
Original Story at insideclimatenews.org